Environmental

                                                                              Licenses




                  The National Environment System (SISNAMA),   Basically, there are three licenses at the federal
                  which includes local, state government envi-  level, which can be issued individually or in suc-             GOVERNMENT              JURISDICTION CONCERNING THE ENVIRONMENTAL
                  ronment agencies, the National Environment   cession, according to the nature, characteristics                    BODY                           LICENSING PROCESS
                  Council (CONAMA) and IBAMA, was created to   and phase of the enterprise or activity:
                  facilitate the licensing process. An environmental                                                    FUNAI – National Indian Foundation  Analyzes the impact on native/indigenous community land
                  license is always required before any potentially   I.  The Preliminary License – valid                                                   and proposals to control and mitigate them.
                  damaging and polluting activities take place in   for no longer than five years;                                                    Analyzes the impact on descendants of slave community (Qui-
                  any part of Brazil.                                                                                    FCP – Palmares Cultural Foundation  lombola) land and proposals to control and mitigate them.
                     Brazil’s environmental legislation is one of   II.  The Installation License -  valid for a
                  the most complete in the world, and its Policy,   minimum time established in the work                IPHAN – Historic and Artistic National   Analyzes the existence of safeguarded cultural assets
                  published in 1981, was the first real breakthrough   schedule, but no longer than six years; and             Heritage Institute      identified in the area of direct influence of the activity and
                  concerning environmental protection and sustain-                                                                                               proposals to safeguard them.
                  ability. The mainstay of the Policy is strict liability   III.  The Operating License – valid for a                                   Analyzes the impact on risk factors for the occurrence of
                  for factories, which, from that moment, became   minimum of four years and maximum of ten                  MS – Ministry of Health   malaria cases if the activity or enterprise is located in areas
                  accountable for the pollution they cause. Soon af-  years.                                                                                      where malaria is endemic.
                  ter, laws were introduced authorizing public pros-
                                                                                16
                  ecutors and NGOs to act in defense of the environ-  The Preliminary License (LP ) certifies the envi-                                Determines and grants an authorization for use of water ac-
                  ment.                                   ronmental feasibility of the business, based on three            ANA – National Water Agency  cording to surface distribution and mediates its multiple uses
                     More recently, many improvements have   aspects: the activity, the location and the impact.                                        (water for drinking, irrigation, industry demands, etc).
                  been made by the Federal Government.  A new   It is important to mention that the LP does
                  Forest Code and a number of regulations regard-  not authorize the installation or operation of the
                  ing environmental licensing proceedings covering   enterprise; its purpose is to authorize the location
                  transmission lines, roads, ports and terminals, as   and design of the project, attest to its environ-
                                                                                                                                                                                         19
                  well as oil and gas exploration and production,   mental viability and set forth the basic require-   Following  submission of the EIA/RIMA  to   Finally, the Operating License (LO ) must be
                  were put into force.                    ments and standards to be met in the next phases           IBAMA, with the corresponding authorization for   applied before initiating the proposed activity. In
                     The Ministry of the Environment has issued   of the licensing process, taking into account the   the enterprise and a public hearing, the applicant   order to get it, a number of reports are required,
                  new rules to decrease the complexity of environ-  different project alternatives and proposals sub-  may obtain a Preliminary License.     describing environmental mitigation measures,
                  mental licensing proceedings at the federal level,   mitted by applicants.                            For enterprises and activities without signif-  including  those  which were  not  mentioned  or
                  as well as to the process up, as well as to assure   During the LP phase, the proposal for the Term   icant environmental impact, IBAMA may cancel   were not accurately detailed during the Installa-
                  the interpretation of the law to mitigate risk for   of Reference (TR ) should be forwarded to IBAMA   the Previous License phase and require instead a   tion License process. Inspection visits may occur
                                                                      17
                  investors. For instance, these rules establish   for preparation of environmental studies. Once    Simplified Environmental Study (EAS) and an En-  at this stage.
                  deadlines for the Brazilian Institute of Environ-  the TR is approved, the applicant should then pre-  vironmental Control Plan (RAP).
                  ment and Renewable Natural Resources (IBAMA)  pare the Environmental Impact Study (EIA) and           As the second phase of the environmental li-
                                                                                                                                                      18
                  to issue environmental licenses, and also to lim-  the Environmental Impact Report (RIMA).         censing process, the Installation Permit (LI ) au-
                  it the number of times that agency may request   Although the documents are submitted to           thorizes the installation of the enterprise/activity
                  additional information and/or studies from en-  IBAMA for analysis, if necessary, other govern-    and the start of construction work in accordance
                  trepreneurs in order to complement the environ-  ment bodies may also contribute to the evalua-    with the specifications contained in previously
                  mental licensing proceedings.           tion, for example:                                         approved plans, programs and projects.

                                                          16  Acronym in Portuguese.                                 18  Acronym in Portuguese.              19  Acronym in Portuguese.
                                                          17  Acronym in Portuguese.
       116                                                                                                                                                                                                  117
   112   113   114   115   116   117   118   119   120   121   122